Perbandingan Biaya dan Waktu Antara Diversion Channel Dengan Pemancangan Steel Sheet Pile Pada Pekerjaan Pemasangan Double U-Ditch Precast

Authors

  • Mukhamad Afif Salim Universitas 17 Agustus 1945 Semarang image/svg+xml
  • Agus B Siswanto 17 Agustus 1945 Semarang University
  • Agung Gagas E 17 Agustus 1945 Semarang University

DOI:

https://doi.org/10.30601/jtsu.v7i2.1689

Abstract

Methods used in the implementation of the project on precast U-ditch installation work, one of which is by steel sheet pile erection method and Diversion Channel method. The analysis data required for the comparison of these two methods is secondary data obtained from the implementing party in the form of RAB, time schedule, implementation picture. In this analysis, alternative methods are planned by comparing in terms of cost and execution time. By analyzing the comparison of steel sheet pile erection method with Diversion Channel method, obtained results on the erection method with Steel sheet pile has a work cost of Rp.7,766,567,860 with an implementation time of 117 days, while with the Diversion Channel method the required cost is Rp.3,894,630,735 with an implementation time of 100 days so that there is a cost efficiency of 49.85% and a faster time of 17 days with diversion channel method.

Author Biography

  • Mukhamad Afif Salim, Universitas 17 Agustus 1945 Semarang
    Department of Civil Engineering

References

Agus B Siswanto,dkk. 2019. Manajemen Proyek. Yogyakarta : Pilar Nusantara

Alfarisy,Fakhrul.2017.Knowledge Management Efisiensi Metode Kerja Diversion Channel Sebagai Metode Penunjang Dalam Pengalihan Aliran. Jakarta : PT. Wijaya Karya

Alya Risdiyanto. (2018). Analisa Perbandingan Biaya dan Waktu Antara Beton Konvensional dan Pracetak. Jurnal Rekayasa dan Manajemen Konstruksi, 6(2), 69-78.

Falah,dkk.2019. Analisis Biaya Pekerjaan Drainase Berdasarkan Metode Pasangan Batu Kali Dengan Precast U-Ditch. Yogyakarta: UII Pers

Kerzner, Harold.2006. Project Management. New Jersey : Inc. Ninth Edition

Hardiyatmo,H.C.2002. Teknik Pondasi 2. Yogyakarta: Beta Offset

Kementrian Pekerjaan Umum. 2013. SNI 03-6456.1-2000 Metode Pengontrolan Sungai Selama Pelaksanaan Konstruksi Bendungan. Bandung: Galang Persada

Downloads

Published

2021-04-22

Issue

Section

Artikel

How to Cite

Perbandingan Biaya dan Waktu Antara Diversion Channel Dengan Pemancangan Steel Sheet Pile Pada Pekerjaan Pemasangan Double U-Ditch Precast. (2021). Jurnal Teknik Sipil Unaya, 7(2), 55-62. https://doi.org/10.30601/jtsu.v7i2.1689